Incoming Inspection Checklist for Bulk Flat Ribbon Cable Reels
Check each reel or traceable lot against the purchase order and cable drawing before releasing it to the cutting line.
Set the acceptance basis before receiving the reels
The order should identify the cable drawing and revision, the approved substitutions, the required put-up and any lot documents. Agree on the sampling plan with the buyer. A dimension check on one offcut covers the sampled location; record any broader checks required by your quality plan.
For example, the 28 AWG, 20-conductor row on Drawing 28 gives a width of 20.0 ± 0.3 mm. If that drawing controls the order, the width limits are 19.7–20.3 mm. An observed width of 20.2 mm is within that interval; the remaining material, identity and packaging checks still need their own evidence.
Reel receiving record
If a reel is on hold
Identify the affected reel and other reels from the same lot. Retain the label, measurement and photo, segregate the material under your receiving procedure, and request a disposition against the controlling drawing before releasing it to cutting.
Agree the checks before placing your order
The RFQ includes the requirements entered here. Use Print checklist for the completed receiving record.